September 01 → November 28 2025
Final Presentation and Report
August 2025
Phase 4 Concept Plans and Operational Plans Reports
June 2025
Phase 3 Interim Waste Management Action Plan and Background Report
May 2025
Additional Engagement
February 21 2025
Draft Project Report Presentation
January 17 2025
Final Interim Waste Management Action Plan
November 29 2024
Phase 2 Findings Summary Report
November 06 2024
Phase 1 Findings Summary Report
October 03 → November 06 2024
Community Site Visits and Engagement Sessions
July 15 2024
Project Kick Off Meeting